FULL TOUR
The Design
Process - PROGRESS OF THE WORK
It was of course expected that
the design be able to be constructed within the allocated
funding and schedule. This too was a major factor in the
continuing re-evaluation and modification of design drawings. It
was quite a task to develop economical structural solutions to
complex structural forms, in the short time allotted. Cardinal's
conceptual design was not approved by Cabinet until November
1983, with site excavation starting the next month and
construction early in 1984. This left just under three years to
meet the original deadline for construction.
 
The massive task of constructing the new
museum began in 1984 and was not completed until 1989.
© Canadian Museum of Civilization,
S2004-1241 (left), S2004-1242 (right), CD2004-1376
|
Because of this and the evolutionary nature of the design
process, a "fast track" method was adopted, whereby
construction proceeded as design decisions were still being made
and incorporated into the architectural drawings. The progress
of design sometimes did not greatly outpace construction. Here,
Cardinal's use of computers in the design process was a great
boon; at times the computer-updated drawings were reprinted
almost daily.
 
The river end of the Museum, at different
stages in construction in 1987.
© Canadian Museum of Civilization,
S2004-1244 (left), S2004-1243 (right), CD2004-1376
|
From the start there were doubts that the 1986 deadline could be
met; the interruption of work through labour disputes did not
help matters. By the end of 1984 it was apparent how seriously
underfunded the two new museum projects were. The completion of
their Cabinet-approved designs was threatened. Options were
considered ranging from not finishing parts of the building, to
finishing it on an extended schedule, to major reductions in the
original standards.
 
(left) The framework of the Grand Hall is
seen, and behind it the three main levels of the public display
wing, at an early stage of construction. (right) The IMAX
theatre is seen in the foreground.
© Canadian Museum of Civilization,
S2004-1246 (left), S2004-1245 (right), CD2004-1376
|
It was decided by the Minister of Communications to transfer
control of the project and of the Canada Museums Construction
Corporation to the Department of Public Works, which had more
construction expertise; this was done in May 1985. A project
review at this stage reached the conclusions that both the
Museum and the Gallery needed to be larger than originally
expected, that the Museum was badly behind schedule, and both
buildings were underfunded, given their size and complexity.
Treasury Board therefore increased the funding for both projects
to $261 million. This injection of funds allowed the
construction of CMC to be completed within a year and a half of
its original deadline.
The copper roofing is laid atop the public
display wing.
© Canadian Museum of Civilization, S2004-1247, CD2004-1376
|
|
|